Company news
Implementation of CTSP development program Q1 2016
In the first three months of 2016 “Container terminal Saint-Petersburg” (CTSP) spent 60,9 million rubles on implementation of the terminal development program.
The major part of the funds, 39,5 million rubles, was spent on maintenance and expansion of the port infrastructure, including repairs of engineering and terminal facilities.
20 million rubles were spent on renewal of the vehicle fleet and equipment, including the agreement on the supply of 45t Kalmar reach stacker, Kalmar terminal tractor and 65t Seacom semi-trailer.
In addition, in the first three months of 2016 the terminal purchased anti-collision laser sensors to improve safety of handling operations: boom-to-ship sensors for installation on the four STS cranes and stack collision prevention sensors for the two RTG cranes.
About 1,4 million rubles was spent on upgrading of the terminal IT infrastructure.